Box Tunnel passes through Box Hill on the Great Western Main Line (GWML) between Bath and Chippenham. The tunnel was the world's longest railway tunnel when it was completed in 1841.
Built between December 1838 and June 1841 for the Great Western Railway (GWR) under the direction of Isambard Kingdom Brunel, the straight tunnel descends on a 1 in 100 gradient from its eastern end. At the time the tunnel's construction was considered dangerous due to its length and the composition of the underlying strata. The west portal is Grade II* listed and the east portal is Grade II listed.
Ammunition was stored near the tunnel during World War II, reusing mine workings. During the 2010s, the tunnel was modified and the track lowered to prepare it for electrification, although in 2016, this plan has been suspended for the time being.
The tunnel would have a gradient of 1 in 100. At the time, the use of such a steep gradient inside the tunnel allegedly provoked criticism by some of Brunel's contemporaries. Box Tunnel would be the longest railway tunnel at almost in length.
The Great Oolite limestone, known as Bath Stone, is easily worked and had been used for construction since Roman Britain times. In the 17th and 18th centuries it was extracted by the room and pillar method and used for many buildings in Bath, Somerset. To assess the geology more accurately, between 1836 and 1837, Brunel sank eight shafts at intervals along the tunnel's projected alignment.
In December 1838, construction started. Work was divided into six sections; access to each was via a ventilation shaft, which ranged in depth from at the eastern end to towards the western end. The men, equipment, materials and of extract had to go in and come out of the shafts assisted by steam engine winches. The shafts were the safety exits from the tunnel.
Candles provided the only lighting in the workings and were consumed at a rate of one tonne per week, which was equalled by the weekly consumption of explosives. Due to the considerable time required for men to enter and exit the workings, Rock blasting took place while they were in the tunnel. This practice and water ingress exceeding the calculated volumes, has been attributed as causing most of the deaths that occurred. About 100 navvy were killed during the tunnel's construction. Additional pumping and drainage were required during and after its construction. Large amounts of water entering the tunnel in the winter months impeded progress.
Once the eastern section had been blasted out, it was cut to form a gothic arch and left unlined. The western section was excavated using picks and shovels and the walls were lined with brick. Over 30 million bricks were used which were manufactured in nearby Chippenham and transported in horse-drawn carts. Horses were used to remove much of the spoil.
The restrictions imposed by the site contributed to a delay in the tunnel's completion. By August 1839, only 40 per cent of the works had been finished. By summer 1840, the to section of the Great Western Main Line (GWML) had been completed, as was the track from Bath to . The Box Tunnel was the last section of the GWML to be finished, although not for lack of effort on the part of Brunel.
During January 1841 Brunel came to an agreement with Burge and Yockney to increase their workforce from to , and the tunnel was completed in April 1841. The completed tunnel was wide and capable of accommodating a pair of broad-gauge tracks. When the ends of the tunnel were joined, there was less than of error in their alignment. Brunel was so delighted that he reportedly removed a ring from his finger and gave it to the works foreman.
After the opening, for several months, work continued to finish the tunnel's western portal near Box, Wiltshire which Brunel had designed in a grand classical style – grander than the eastern portal as it is in full view of the London to Bath road. The height of the opening is far in excess of what was required (and indeed reduces once inside), but it gives the feel of a generous celebratory monument to a new form of travel. That height has been further accentuated with the 2015 lowering of the trackbed for overhead line to be installed. The eastern portal at Corsham has a more modest brick face, with rusticated stone dressings.
Commentators and critics voiced concerns and disapproval about the unlined section of the tunnel; they believed that it lacked solidity and was a danger to traffic. The GWR responded to these complaints by building a brick arch underneath part of the unlined section close to the entrance which was prone to frost damage. Some areas of the tunnel remain unlined.
During the 1930s, Tunnel Quarry was renovated by the Royal Engineers as one of the three major stockpiles. During November 1937, the GWR was contracted to build a raised twin-loading platform at Shockerwick for Monkton Farleigh and two sidings branching from the Bristol–London mainline just outside the tunnel's eastern entrance at . below and at right angles to this point, the War Office had built a narrow-gauge wagon-sorting yard which accessed a tunnel, built by the Cementation Company, descending at a rate of 1 in 8.5 to the Central Ammunition Depot in the former quarry workings. The logistics operation was designed to cope with a maximum of tons of ammunition per day.
A Royal Air Force station, RAF Box, was established and used an area of the tunnels. In response to the Bristol Blitz, during 1940, Alfred McAlpine developed a fallback aircraft engine factory for use by the Bristol Aeroplane Company (BAC), although it never went into production. BAC used the facility to accommodate the company's experimental department, which was developing an engine to power bomber aircraft and the Bristol Beaufighter.
The CAD was closed at the end of the war but was maintained in operational condition until the 1950s. The sidings were cleared, and saw no further use until the mid-1980s when a museum was opened on the site for a short period. During the post-war years, portions of the ammunition depot were redeveloped for other facilities, including the Central Government War Headquarters, RAF No.1 Signal Unit, Controller Defence Communication Network and the Corsham Computer Centre.
As of the present day, the only element of the complex that remains is the former computer centre. The visible north end of the tunnel has been sealed by concrete and rubble. The former CAD has been reused as a secure commercial document storage facility.
Opening
Brunel's birthday
Defence use
Electrification
Geographical location
See also
Citations
Bibliography
External links
|
|